The government awards contracts to companies with histories of misconduct such as contract fraud and environmental, ethics, and labor violations. In the absence of a centralized federal database listing instances of misconduct, the Project On Government Oversight (POGO) is providing such data. We believe that it will lead to improved contracting decisions and public access to information about how the government spends hundreds of billions of taxpayer money each year on goods and services. Report an instance of misconduct »
General Dynamics
Final Analysis Communication Systems v. General Dynamics (Breach of Contract)
Date: 04/17/2006 (Date of Final Judgment)
Misconduct Type: Poor Contract Performance
Enforcement Agency: Non-Governmental
Contracting Party: Non-Governmental
Court Type: Civil
Amount: $11,870,000
Disposition: Judgment Against Defendant
Synopsis: Final Analysis Communication Systems, Inc. brought claims against General Dynamics for breach of contract, fraud, tortuous interference with contractual and business relations, fraudulent inducement, negligent misrepresentation and breach of warranty. In September 2005, a jury rendered a verdict against General Dynamics in the amount of $138 million and a verdict in its favor in the amount of $8 million on their counterclaims. The following April, the judge entered a final judgment in favor of FACS in the amount of $19,870,000 and in favor of General Dynamics in the amount of $8 million.