The federal government routinely awards contracts to companies with histories of misconduct, including contract fraud and other violations. POGO believes that providing this website will help to improve contracting decisions and increase public knowledge of how the government spends billions of taxpayer dollars each year. Read more…

Overcharges in Providing Fuel to a Police Academy in Amman, Jordan

The January 30, 2005 Special Inspector General for Iraq Reconstruction (SIGIR) report to Congress notes that an audit requested by the Bureau of International Narcotics and Law Enforcement Affairs (INL) estimated that DynCorp may have overcharged the government as much as $600,000 in providing fuel to the INL-administered police academy in Amman, Jordan. The State Department Inspector General’s audit of the contract confirmed INL’s estimate of overcharges and found a basis for an additional claim of $85,000. DynCorp reimbursed the government $600,824.

Misconduct Type
Cost/Labor Mischarge
Enforcement Agency
Multiple Agencies
Contracting Party
State Dept.
Court Type
N/A
Disposition
Restitution
Date of Report
1/30/2005
Contractors Involved Penalty
Total
DynCorp International Inc. $600,824
Further Information Released
State Dept. OIG Report 4/16/2008
SIGIR Report (p. 25 of 119) 7/20/2007